The redevelopment of the former Buffalo Color site involves demolition of nearly all of the former chemical plant. Major buildings such as the Boiler House may be reused. Site preparation began in late April. Demolition began in June 2009.
Beginning the week of February 15, 2010, South Buffalo Development began bringing clean soil to the former Buffalo Color site. Some of the clean fill will be used immediately; some of it will be used at a later date.
The site will be remediated to government environmental standards. SBD will redevelop the site for commercial and light industrial use.
The redevelopment project includes:
Demolition activities will take approximately 12 months to complete. The anticipated demolition schedule is shown below.

Anticipated Demolition Schedule